1.由安装施工方与建设单位、供货单位共同对液压升降平台以及零部件进行清点交接。By the installation of the construction side and the construction unit, the supply unit of hydraulic lifting platform and parts of the inventory handover.
2.经过吊装运输到现场,液压升降平台设备的开箱检查和保管。After lifting the transport to the site, the hydraulic lifting platform of equipment inspection and keep out of the box.
3.设备基础。设备基础是否达到基础要求的位置,液压升降平台安装施工与土建施工交接。Equipment foundation. Whether the equipment foundation meets the basic requirements, the installation of the hydraulic lifting platform is connected with the civil construction.
4.起重、测量、切割、焊接等液压升降平台工具设备组织准备。Preparation of lifting, measuring, cutting, welding and other hydraulic lifting platform equipment.
5.正式安装钱准备过程中首先必须准备好技术施工方案。只有根据实际情况做好充分计划,尤其是大型液压升降平台的安装施工,更要详细做好施工方案才能保证客户要求。The formal installation of money preparation process must first be ready for technical construction program. Only in accordance with the actual situation to do a good job, especially the large-scale hydraulic lifting platform installation construction, but also to do a good job in detail to ensure that the construction of customer requirements.